Press Line Relocation Project
Press Line Relocation Project
QOS has successfully completed a turnkey project involving the disassembly, transportation, and installation of 400-ton presses equipped with hydraulic tie-rods, featuring 4-stage and 2-stage mechanisms, with a maximum weight of 50 tons and a height of 6.5 meters.
Responsibilities of the QOS Team:
- Mechanical and electrical tagging and disassembly of all machinery and equipment
- Transporting the dismantled equipment to the new installation site
- Implementation of floor markings in accordance with the approved layout
- Mechanical, electrical, and plumbing installations of machinery and equipment in the new facility
- Conducting cold tests (I/O tests) on equipment for press lines
- Turnkey commissioning of presses.
QOS Team Composition:
- 1 Engineer
- 30 specialized staff members were assigned to the task.
Equipment Used:
- 3-, 5-, and 10-ton forklifts
- 75-ton and 100-ton Hi-Up cranes
- 6–8 m cherry picker ve 8–10 m manliftler
100% Customer Satisfaction
On-Time Delivery
Expert Team